CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
Where they are
Who receives the most
- 01Ministerio de Fomento3€451.1m
- 02ADIF17€300.9m
- 03Gestor Despliegue (ENAIRE)7€280.3m
- 04ADIF Alta Velocidad7€216.6m
- 05ADMINISTRADOR DE INFRAESTRUCTURAS FERROVIARIAS1€77.8m
- 06BE CHARGE SRL1€50.4m
- 07Iberdrola Clientes SA (IBCLI)1€40.6m
- 08European High Power Charging Beteiligungsgesellschaft mbH1€39.1m
- 09ENAIRE2€37.7m
- 10Autoridad Portuaria de Bilbao2€37.5m
By status
- Completed 127€1.4bn
- Ongoing 68€870.7m
- Terminated 18€128.7m
- In preparation 8€72.7m
By mode
- Rail 47€1.1bn
- Road 74€469.3m
- Air 19€372.7m
- Maritime 49€301m
- Multimodal 29€180.8m
- Inland waterways 2€2.3m
- No mode 1€0
By corridor
- Atlantic Corridor 31€825.4m
- Outside the corridors 97€691.2m
- Mediterranean Corridor 46€558.3m
- Atlantic and Mediterranean 47€384m
Projects
221 projects · funding €2.5bn
ATLANTIC CORRIDOR: SECTION BERGARA-SAN SEBASTIAN-BAYONNE. BERGARA JUNCTION TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. PHASE 2
€145.4m
OngoingADIF Alta Velocidad · Rail · Atlantic Corridor · call CEF-T-2021-COREGEN · Jan 2021 → Dec 2025 · investment €290.8m
Mediterranean corridor. Bilbao-Pamplona-Zaragoza-Sagunto line. Section Zaragoza-Teruel-Sagunto. Electrification works
€77.8m
OngoingADMINISTRADOR DE INFRAESTRUCTURAS FERROVIARIAS · Rail · Mediterranean Corridor · call CEF-T-2023 · Oct 2024 → Dec 2028 · investment €259.2m
TANGERINE
€40.6m
OngoingIberdrola Clientes SA (IBCLI) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €40.6m
Sagunto Multimodal Logistic Platform
€27.6m
OngoingGeneralitat Valenciana · Rail · Mediterranean Corridor · call CEF-T-2023 · Feb 2024 → Sept 2026 · investment €92.1m
Onshore power supply for container ships, ferries and cruise ships in the Port of Valencia
€23.8m
OngoingFUNDACION DE LA COMUNIDAD VALENCIANA PARA LA INVESTIGACION, PROMOCION Y ESTUDIOS COMERCIALES DE VALENCIAPORT · Maritime · Mediterranean Corridor · call CEF-T-2023 · Feb 2024 → Dec 2028 · investment €78.7m
Accelerate Europe’s key infrastructure - GENERAL
€23.4m
OngoingTesla Italy SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €23.4m
PALLANTIA
€22.5m
OngoingGrupo Easycharger SA · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €22.5m
ATLANTIC CORRIDOR. TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. SECTION ATXONDO - ABADIÑO. PHASE 2
€22m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-COREGEN · Feb 2023 → Jan 2027 · investment €73.4m
PALMAS PORT SPHINX DIKE PHASE IV
€20.6m
OngoingA.P. Las Palmas · Maritime · Atlantic Corridor · call CEF-T-2021-COREGEN · Mar 2021 → Jul 2025 · investment €29.5m
Ponentia-La Melusa international railway multimodal terminal
€19.5m
OngoingPONENTIA LOGISTICS S.A · Multimodal · Mediterranean Corridor · call CEF-T-2023 · Sept 2024 → Dec 2026 · investment €64.2m
inteGrated modeRnisation of the EuropEan Network for CNS
€18.3m
OngoingEUROCONTROL - EUROPEAN ORGANISATION FOR THE SAFETY OF AIR NAVIGATION · Air · Outside the corridors · call CEF-T-2023 · Feb 2024 → Dec 2028 · investment €35.5m
CADIZ CONTAINER MULTIMODAL TERMINAL AND LAND ACCESS. PHASE II
€15.6m
OngoingAutoridad Portuaria de la Bahía de Cádiz · Maritime · Atlantic Corridor · call CEF-T-2021-COMPGEN · Oct 2022 → Jun 2026 · investment €52.1m
Smart Electrification Infrastructure for the Urban Surface
€15.4m
OngoingEMT · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €51.2m
Phase 1 and 2 of the Plan to implement Shore-to-Ship Power Supply at the Port of Barcelona
€15.2m
OngoingAUTORITAT PORTUARIA DE BARCELONA · Maritime · Mediterranean Corridor · call CEF-T-2023 · Feb 2024 → Dec 2028 · investment €49.8m
DElegation through VIrtual Centres
€14.8m
OngoingENAIRE · Air · Outside the corridors · call CEF-T-2022-SIMOBGEN · Nov 2023 → Oct 2026 · investment €29.6m
Extended Communications in vHf Over Enhanced Satellite segment
€14.6m
OngoingStartical SL · Air · Outside the corridors · call CEF-T-2021-SIMOBGEN · Mar 2022 → Dec 2025 · investment €28m
Bilbao Port Net-Zero Green Onshore Power System for Comprehensive Support & Core TEN-T Cold Ironing Capabilities Expansion in the Atlantic Corridor
€14.3m
OngoingAutoridad Portuaria de Bilbao · Maritime · Atlantic Corridor · call CEF-T-2021-COREGEN · Feb 2022 → Jan 2026 · investment €47.5m
INTERMODAL TERMINAL OF MURCIA AND ITS RAIL LINK
€13.9m
OngoingConsejería de Fomento e Infraestructuras (C. A. Región de Murcia) · Multimodal · Mediterranean Corridor · call CEF-T-2021-COREGEN · Oct 2022 → Nov 2025 · investment €46.1m
HY2MOVE1
€12.8m
OngoingRepsol Comercial de Productos Petrolíferos (RCPP) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Dec 2022 → Oct 2025 · investment €42.8m
Accelerating on-the-go EV ultra-fast charging network in Italy, France, Spain and Portugal
€11.4m
OngoingAtlante SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €11.4m
SCALE
€8.1m
OngoingMINISTERE DE LA TRANSITION ECOLOGIQUE ET DE LA COHESION DES TERRITOIRES · Road · Outside the corridors · call CEF-T-2023 · Sept 2024 → Dec 2028 · investment €16.1m
2023 Arnedo Secure Ecopark
€7.9m
OngoingINMO-ARNEDO S.L.U · Road · Atlantic Corridor · call CEF-T-2023 · Oct 2024 → Mar 2026 · investment €18.5m
INSPIRA MADRID
€7.4m
OngoingFRV-X · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €24.6m
Mediterranean-Atlantic Transport Intelligent Systems
€6.7m
OngoingASFA · Road · Atlantic and Mediterranean · call CEF-T-2022-SIMOBGEN · Jan 2023 → Jan 2027 · investment €13.5m
Intermodal Platform of the Port of Huelva II: a boost to multimodality, connectivity and sustainability
€6.7m
OngoingAutoridad Portuaria de Huelva · Multimodal · Atlantic Corridor · call CEF-T-2022-COREGEN · Oct 2022 → Apr 2025 · investment €22.4m
Design and deployment of On-shore powersupply in Algeciras Port
€6.4m
OngoingAP BAHIA DE ALGECIRAS · Maritime · Atlantic and Mediterranean · call CEF-T-2022-COREGEN · Mar 2023 → Jan 2027 · investment €20.3m
Next Wav-E: Developing an EU-wide network of electric vehicles’ high-power charging infrastructure for the electrification of mobility and decarbonisation of the road transport sector
€6m
OngoingENEL X WAY · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Nov 2022 → Nov 2025 · investment €6m
Extension of the Pechina quay. 1st Phase.
€6m
OngoingAUTORIDAD PORTUARIA DE ALMERIA · Maritime · Outside the corridors · call CEF-T-2023 · Oct 2024 → Mar 2028 · investment €19.9m
Southern European EV fast-charging network (Italy, France, Spain)
€5.8m
OngoingAtlante SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025 · investment €5.8m
CP1 Deployment – Synchronised Modernisation of ATM
€5.6m
OngoingEurocontrol · Air · Outside the corridors · call CEF-T-2022-SIMOBGEN · Jan 2023 → Dec 2027 · investment €11m
Port Real-time Information Smart Management; PRISMA
€5.1m
OngoingAUTORIDAD PORTUARIA DE SEVILLA · Maritime · Atlantic and Mediterranean · call CEF-T-2023 · Jan 2024 → Dec 2027 · investment €10.3m
Improvements on the road access to the maritime port of Bilbao and its connectivity with other critical infrastructures in the Biscay region
€5.1m
OngoingDIPUTACION FORAL DE BIZKAIA · Road · Atlantic Corridor · call CEF-T-2022-MILMOB · Sept 2022 → Mar 2026 · investment €10.2m
Safe Parking for Trucks (SSTPA) in the LAA of Murcia
€5m
OngoingConsejería de Fomento e Infraestructuras · Road · Mediterranean Corridor · call CEF-T-2022-SAFEMOBGEN · Nov 2023 → Nov 2025 · investment €9.9m
Ultrafast e-mobility infrastructure in ES-PT Mediterranean
€4.5m
OngoingCEPSA COMERCIAL PETROLEO SA (CCP) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €4.5m
Optimization of the TRAffic MAnagement and infrastructure capacity in the port of Valencia
€4.1m
OngoingFUNDACION DE LA COMUNIDAD VALENCIANA PARA LA INVESTIGACION,PROMOCION Y ESTUDIOS COMERCIALES DE VALENCIAPORT · Multimodal · Mediterranean Corridor · call CEF-T-2023 · Mar 2024 → Dec 2026 · investment €8.2m
Temple & Mare Nostrum SSTPA Extensions A7
€4m
OngoingTRANSPORTES CALSINA Y CARRE SOCIEDAD LIMITADA · Road · Mediterranean Corridor · call CEF-T-2023 · Feb 2024 → Nov 2026 · investment €8m
Works for basic maritime infrastructures, heel and RO-RO ramp, at Raos 9 quay to improve the efficiency of the port of Santander (Cantabria)
€3.5m
OngoingAUTORIDAD PORTUARIA DE SANTANDER · Maritime · Atlantic Corridor · call CEF-T-2023 · Aug 2024 → Jan 2026 · investment €11.9m
Upgrade and extension of a safe and secure parking area in the Spanish-French border region on the Mediterranean TEN-T Core Network Corridor
€3.5m
OngoingTransportes Calsina y Carre SL · Road · Mediterranean Corridor · call CEF-T-2021-SAFEMOBGEN · Jun 2021 → Jun 2024 · investment €7.9m
Spanish Airports' decarbonization through the implementation of electric vehicles of handling operators
€3.4m
OngoingAENA SME SA · Air · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Dec 2024 · investment €11.3m
Smart European Maritime Space
€3.2m
OngoingFUNDACION DE LA COMUNIDAD VALENCIANA PARA LA INVESTIGACION, PROMOCION Y ESTUDIOS COMERCIALES DE VALENCIAPORT · Maritime · Outside the corridors · call CEF-T-2023 · Feb 2024 → Sept 2026 · investment €6.4m
Spanish Safe and Secure Truck Parking Area Network
€3.1m
OngoingGP Límite Andamur SL · Road · Atlantic and Mediterranean · call CEF-T-2021-SAFEMOBGEN · Mar 2022 → Sept 2025 · investment €6.3m
PCZ 2022: Bridging the cross border missing link between FR & SP: Pau-Canfranc-Zaragoza
€3m
OngoingRegión Nouvelle-Aquitaine · Rail · Outside the corridors · call CEF-T-2022-SIMOBGEN · Feb 2023 → Apr 2026 · investment €6.1m
DATA SPACE 4 MOBILITY MODELS INTEGRATION
€3m
OngoingESTACIONAMIENTOS Y SERVICIOS, S.A.U · Multimodal · Outside the corridors · call CEF-T-2023 · Jun 2024 → May 2027 · investment €6m
U-space European COMmon dEpLoyment
€2.9m
OngoingEUROCONTROL · Air · Outside the corridors · call CEF-T-2021-SIMOBGEN · Nov 2022 → Oct 2025 · investment €5.7m
Heavy Wav-E, Mediterranean ultra-fast charging arteria for electric heavy-duty and light-duty vehicles
€2.8m
OngoingENEL X WAY · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Jul 2023 → Dec 2025 · investment €2.8m
European flagship action for cold ironing Works in Gijon Port
€2.6m
OngoingAUTORIDAD PORTUARIA DE GIJON · Maritime · Atlantic Corridor · call CEF-T-2023 · Oct 2024 → Dec 2027 · investment €8.6m
Air Products European HRS Network
€2.5m
OngoingAir Products Nerderland BV · Road · Outside the corridors · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Sept 2026 · investment €8.5m
Safe and secure parking area in Pinto in the South of Madrid on the Atlantic TEN-T Core Network Corridor
€2.4m
OngoingAtalaya Patrimonio Inmobiliario S.L · Road · Atlantic and Mediterranean · call CEF-T-2023 · Sept 2024 → Oct 2025 · investment €4.9m
Study of gauges for the development of Rail Motorway Algeciras - Zaragoza
€2.4m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.9m
Air Products' European HRS Network
€2.3m
OngoingAir Products Nederland BV · Road · Mediterranean Corridor · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €7.5m
Works for gauge adaptation in railway line Medina del Campo – Salamanca- Fuentes de Oñoro and services to follow-up works
€2.2m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.5m
Digital Capacity Management Implementation 2024-2026
€2.1m
OngoingRAILNETEUROPE-VEREINIGUNG ZUR FORDERUNG DES INTERNATIONALEN VERKEHRS AUF DER EISENBAHNINFRASTRUKTUR · Rail · Outside the corridors · call CEF-T-2023 · Apr 2024 → Dec 2027 · investment €4.1m
Support to Spain for CEF related activities, participation in the RFC and CNC, and on TENtec
€1.9m
OngoingMITMA · Multimodal · Outside the corridors · call CEF-T-2021-TAGENEA · Jan 2021 → Dec 2025
Upgrade of Zaragoza's terminal rail facilities Upgrade of TmZ terminal rail facilities for 750 m trains and new North rail connection to become a through terminal and avoid bottlenecks in the accesses
€1.8m
OngoingTerminal Marítima de Zaragoza SL · Multimodal · Mediterranean Corridor · call CEF-T-2022-COREGEN · Jan 2023 → Feb 2026 · investment €6m
Accelerating Europe’s key infrastructure phase II
€1.8m
OngoingTesla Motors Netherlands B.V · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €1.8m
CP1 Deployment – Synchronised Modernisation of ATM (Part 2)
€1.3m
OngoingEUROCONTROL - EUROPEAN ORGANISATION FOR THE SAFETY OF AIR NAVIGATION · Air · Outside the corridors · call CEF-T-2023 · Feb 2024 → Dec 2027 · investment €2.5m
ANalysis of AI techniqueS in data management for public transport digitaliSation
€1.2m
OngoingAVANZA SPAIN SL · Road · Outside the corridors · call CEF-T-2023 · Oct 2024 → Sept 2027 · investment €2.5m
Urban Hydrogen Refuelling Stations to Transform Madrid's Transportation
€1.2m
OngoingMolgas Energía SA · Road · Outside the corridors · call CEF-T-2021-AFIFGEN-3er. corte · Nov 2022 → Feb 2024 · investment €4.1m
eCall NG
€878,500
OngoingITS MOBILITY GMBH · Road · Outside the corridors · call CEF-T-2023 · Mar 2024 → Jun 2027 · investment €1.8m
Desarrollo del Corredor de Carga Ferroviaria Atlántico "Sines-Lisboa / Leixoes - Madrid- Medina del Campo / Bilbao / San Sebastián-Irún-Burdeos-París / Le Havre / Metz - Estrasburgo / Mannheim / Sines-Elvas / Algeciras"
€765,000
OngoingGEIE Corridor Ferroviaire de Marchandises 4 (GEIE CFM4) · Rail · Atlantic Corridor · call 2014 · Nov 2015 → Mar 2021 · investment €1.5m
European Sky Multilink ATN
€549,605
OngoingEuropean Satellite Services Provider SAS · Air · Outside the corridors · call CEF-T-2022-SIMOBGEN · Jan 2024 → Dec 2026 · investment €1.1m
C-Roads Extended
€369,900
OngoingAUSTRIATECH - GESELLSCHAFT DES BUNDES FUR TECHNOLOGIEPOLITISCHE MASSNAHMEN GMBH · Road · Outside the corridors · call CEF-T-2023 · Sept 2024 → Aug 2027 · investment €739,800
Highly Efficient Green Operations
€63,500
OngoingAIRBUS · Air · Outside the corridors · call CEF-T-2021-SIMOBGEN · Nov 2022 → Oct 2025 · investment €127,000
EUROP-E, Proyecto de despliege europeo de ultracargadores para vehiculos eléctricos
€39.1m
OngoingEuropean High Power Charging Beteiligungsgesellschaft mbH · Road · Outside the corridors · call 2017 · Jul 2017 → Dec 2021
AMBRA-E lectrify Europe
€14.2m
OngoingEnel X S.r.l. (Italia) · Road · Atlantic and Mediterranean · call 2017 · Sept 2018 → Dec 2022
Expand-E General: EXpanding Performance and Network Density – Electric
€28.2m
OngoingIONITY GMBH · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025
Ultra Fast in Europe
€50.4m
OngoingBE CHARGE SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025
European Hydrogen Network by Hype
€18.1m
OngoingHype Assets · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Nov 2022 → Nov 2025
First methanol bunkering infrastructure in Huelva as part of the Andalusian Green Hydrogen Valley
€16.6m
In preparationCEPSA · Maritime · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €55.2m
Electric charging infrastructure for APMT Spanish gateways’ port equipment
€16.5m
In preparationAPMTB · Maritime · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €55m
First ammonia bunkering infrastructure in Algeciras as part of the Andalusian Green Hydrogen Valley
€13.6m
In preparationCEPSA · Maritime · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €45.4m
Deployment of a network of hydrogen fuelling stations of 1.000kg/day of capacity in Spain
€8m
In preparationSCALE GAS SOLUTIONS S.L. · Road · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €26.8m
Deployment of Reliable Infrastructure for Vehicle Electrification
€6.5m
In preparationREPSOL COMERCIAL DE PRODUCTOS PETROLIFEROS SA · Road · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €6.5m
MILES General: Mobility Infrastructure for Logistics - Electric & Sustainable in AT, BE, DE, DK, ES, FR, IT, NL, and SE
€4.6m
In preparationMilence Infrastructure Holding B.V · Road · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €15.3m
ACTIVA
€4.2m
In preparationHVR Energy · Road · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €14m
Electra European ultra-fast recharging network
€2.7m
In preparationELECTRA · Road · Outside the corridors · call CEF-T-2024-AFIFGEN-1er corte · investment €2.7m
Corredor atlántico: tramo Bergara-San Sebastián- Bayona. Estudios y obras y servicios de seguimiento de obras. Fase 1.
€448.1m
CompletedMinisterio de Fomento · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2023 · investment €1.1bn
SESAR Deployment Programme Implementation - 2017
€228.2m
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2017 · Apr 2018 → Dec 2021 · investment €457.7m
Implementación del ancho UIC (fase 1) en el tramo Valencia-Tarragona-Barcelona del corredor Mediterráneo.
€124.5m
CompletedADIF · Rail · Mediterranean Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €311.2m
Implantacion del ancho UIC en el tramo Castellbisbal-Vilaseca. Corredor Mediterráneo.
€57m
CompletedADIF · Rail · Mediterranean Corridor · call 2017 · Jul 2017 → Dec 2024 · investment €285m
Mediterranean Corridor. Section Valencia-Sagunto-Castellón. Implementation of UIC gauge. Phase 2."
€41.5m
CompletedADIF · Rail · Mediterranean Corridor · call 2019 · Feb 2020 → Dec 2024 · investment €103.8m
Aplicación del programa de despliegue sesar 2016 - grupo 1: generalidades
€34.9m
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2016 · Feb 2017 → Dec 2023 · investment €88m
Actualización y retroadaptación del ERTMS embarcado en los vehículos de renfe
€28m
CompletedRENFE F y M · Rail · Outside the corridors · call 2015 · Feb 2016 → Dec 2024 · investment €56m
Pruebas futuras del Puerto de Bilbao perteneciente a la red básica del corredor atlántico.
€23.2m
CompletedAutoridad Portuaria de Bilbao · Maritime · Atlantic Corridor · call 2014 · Jan 2015 → Oct 2021 · investment €116.2m
Solicitud conjunta para la implementación del pdp - grupo 1
€22.8m
CompletedENAIRE · Multimodal · Outside the corridors · call 2014 · Jan 2014 → Dec 2020 · investment €45.7m
Conexión ferroviaria Aveiro-Salamanca-Medina del Campo: obras en instalaciones y servicios de energía para trabajos de seguimiento.
€19.6m
CompletedADIF · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €49m
Línea ferroviaria de alta velocidad Bilbao-Vitoria - Obras de plataforma en las subsecciones Elorroio-Atxondo y Atxondo-Abadino y trabajos de seguimiento.
€18.1m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · Dec 2015 → Dec 2020 · investment €90.4m
CORE LNGas - Corredores Red Básica Gas Natural Licuado (obras)
€16.5m
CompletedEnagas Transporte, S.A.U. · Multimodal · Outside the corridors · call 2014 · Jan 2014 → Dec 2021 · investment €33.1m
IBERDROLA SMART MOBILITY
€13.4m
CompletedIBERDROLA CLIENTES, S.A. · Road · Atlantic and Mediterranean · call 2019 · Mar 2020 → Dec 2022 · investment €89.2m
Aplicación del programa de despliegue SESAR 2015 - grupo 2
€12.6m
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2015 · Feb 2016 → Dec 2024 · investment €40.3m
LNGHIVE2 VESSEL DEMAND: GREEN AND SMART LINKS
€11.8m
CompletedBalearia · Maritime · Atlantic and Mediterranean · call 2017 · Apr 2018 → Jul 2021 · investment €59m
Mejora de la conexión ferroviaria interior y de la accesibilidad marítima al Puerto de Valencia (CONNECT VALENCIAPORT).
€11.6m
CompletedFundación Valenciaport · Maritime · Mediterranean Corridor · call 2014 · Jan 2014 → Dec 2023 · investment €55.9m
Corredor Atlántico. Suministro, instalaciones eléctricas y obras acústicas en la sección Chamartín-Atocha- Torrejón de Velasco del HSRL Madrid-Lisboa y Madrid- Bobadilla.
€11.4m
CompletedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2014 · May 2015 → Mar 2018 · investment €38.2m
LNGHIVE2 Algeciras - A Flex LNG bunkering facility in the port of Algeciras Bay
€11.3m
CompletedENAGAS · Maritime · Atlantic and Mediterranean · call 2019 · Jul 2020 → May 2023 · investment €56.5m
Retroadaptación del ERTMS embarcado en los vehículos de renfe
€11.3m
CompletedRENFE-FABRICACIÓN Y MANTENIMIENTO SOCIEDAD MERCANTIL ESTATAL,S.A. · Rail · Outside the corridors · call 2016 · Feb 2017 → Dec 2024 · investment €22.5m
Implementation of Voice over IP (VoIP) in Barcelona ACC
€10.8m
CompletedSESAR Deployment Manager (NATs en route) · Air · Mediterranean Corridor · call 2017 · Jan 2018 → Dec 2023 · investment €21.7m
TB CLEAN URBAN TRANSPORT FLEET RENEWAL
€9.2m
CompletedTransports de Barcelona S.A · Road · Mediterranean Corridor · call 2019 · Jan 2020 → Dec 2024 · investment €47.6m
LNGHIVE2 Barcelona- An efficient LNG bunker barge in the port of Barcelona
€9.2m
CompletedENAGAS · Maritime · Mediterranean Corridor · call 2019 · Mar 2020 → Dec 2023 · investment €45.8m
C-ROADs España
€9m
CompletedDirección General de Tráfico (DGT) · Road · Outside the corridors · call 2016 · Feb 2017 → Jun 2021 · investment €18m
Despliegue de ERTMS en el tramo Valladolid-Burgos
€7.8m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2014 → Dec 2022 · investment €15.6m
Plataforma logística intermodal en el suroeste de Europa
€7.6m
CompletedGobierno de Extremadura · Multimodal · Atlantic Corridor · call 2014 · Apr 2014 → Sept 2022 · investment €35.8m
Project Everest
€7.3m
CompletedNORDIAN CPO, SL · Road · Atlantic and Mediterranean · call 2019 · Aug 2020 → Jun 2023 · investment €48.9m
Electrification and Signalling works in Crossborder Section Guillarei Tui
€6.5m
CompletedADIF · Rail · Outside the corridors · call 2019 · Sept 2019 → Dec 2023 · investment €16.3m
[LNGHIVE2 Santander] Development of LNG bunkering infrastructure in Santander, a strategic port in the North of Spain
€6.3m
CompletedREPSOL · Maritime · Outside the corridors · call 2019 · May 2019 → Jun 2023 · investment €31.6m
Atlantic Corridor. High Speed line Sines/Lisboa-Madrid. Madrid urban node. Study of the Railway Complex of Atocha Station (Phase 3)
€6m
CompletedADIF · Rail · Atlantic Corridor · call 2019 · Feb 2020 → Dec 2023 · investment €12m
Despliegue de ERTMS en las líneas de cercanías de Barcelona
€5.2m
CompletedADIF · Rail · Mediterranean Corridor · call 2014 · Nov 2015 → Dec 2022 · investment €10.4m
Estudios y obras para conexiones por ferrocarril de 4 terminales de carga existentes a lo largo del Corredor Mediterráneo en España por GRUPO ALONSO
€5.2m
CompletedServicios Terrestres y Marítimos S.A. (Grupo ALONSO) · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2022 · investment €21.1m
Operaciones sostenibles de GNL para puertos y transporte marítimo - Acciones piloto innovadoras (GAINN4MOS)
€5.1m
CompletedFundación Valenciaport · Maritime · Outside the corridors · call 2014 · Jan 2015 → Sept 2019 · investment €10.3m
Eco-gate: corredores europeos para la eficiencia del transporte de gas natural
€5.1m
CompletedGas Natural Madrid SDG, S.A. · Road · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2021 · investment €10.2m
Madrid Vicálvaro Freight Railway Terminal.Works Phase 1.Subphase 1A. Mediterranean Corridor. Rail Works and Road Studies
€4.5m
CompletedADIF · Multimodal · Mediterranean Corridor · call 2018 · Nov 2018 → Dec 2023 · investment €21.1m
FEDeRATED
€4.4m
CompletedMINISTERIE VAN INFRASTRUCTUUR EN WATERSTAAT (PAÍSES BAJOS) · Multimodal · Outside the corridors · call 2018 · Jan 2019 → Mar 2024 · investment €8.9m
Actualización de todas las líneas de alta velocidad españolas a la versión 2.3.0.d. De ERTMS (ETCS+GSMR) 2ª fase
€4.2m
CompletedADIF · Rail · Outside the corridors · call 2014 · Apr 2014 → Jun 2022 · investment €8.4m
ADS-B Deployment in SW FAB
€3.8m
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2017 · Apr 2018 → Dec 2023 · investment €7.6m
Development of an innovative hydrogen infrastructure hub for TMB public buses and private users in the city of Barcelona
€3.7m
CompletedIberdrola Clientes, S.A. · Road · Outside the corridors · call 2019 · Feb 2021 → Dec 2024 · investment €18.7m
Desarrollo ferroviario en el Puerto de Castellón: Red Ferroviaria de la Dársena Sur, Puente ferroviario y Conexión norte
€3.7m
CompletedAutoridad Portuaria Castellón · Maritime · Outside the corridors · call 2019 · Jan 2020 → Dec 2024 · investment €18.7m
Proyecto de validación del Gestor de Tráfico Marítimo.
€3.6m
CompletedAdministración Marítima Sueca · Maritime · Outside the corridors · call 2014 · Jan 2015 → Dec 2018 · investment €7.2m
ATL_Freight_South_access_to_Bilbao_Port
€3.5m
CompletedDirección de Infraestructuras del Transporte. Gobierno Vasco · Rail · Outside the corridors · call 2020 · Mar 2021 → Dec 2024 · investment €7m
Development of a network of alternative fuel technology in the Atlantic and Mediterranean corridors across Spain
€3.3m
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLÍFEROS, S.A. (RCPP) · Road · Atlantic and Mediterranean · call 2019 · Jul 2020 → Dec 2024 · investment €21.9m
Cleanport - combustibles alternativos y soluciones para el planchado en frío del puerto: normalización del marco reglamentario obra y demostración de la viabilidad de la explotación
€3.2m
CompletedGAS NATURAL SDG, S.A. · Maritime · Mediterranean Corridor · call 2014 · Jan 2014 → Dec 2018 · investment €6.4m
Arco atlantico fase II
€3m
CompletedDepartment for Transport UK · Road · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2017 · investment €14.8m
LNGHIVE2 INFRASTRUCTURE AND LOGISTICS SOLUTIONS
€2.9m
CompletedEnagas Transporte, S.A.U. · Maritime · Atlantic and Mediterranean · call 2017 · Sept 2018 → Dec 2023 · investment €14.7m
Improvement of rail connectivity, safety and security of the port of Sagunto (CONNECTING SAGUNTO)
€2.8m
CompletedFundación Valenciaport · Maritime · Outside the corridors · call 2019 · Apr 2019 → Dec 2024 · investment €13.6m
Setting up two safe and secure parking areas in the Spanish-French border region
€2.8m
CompletedAgencia Guipuzcoana de lnfraestructuras S.A. (BIDEGI S.A.) · Road · Atlantic Corridor · call 2019 · Feb 2020 → Oct 2020 · investment €15.2m
Interoperability of the rail system with TAF TSI in TEN-T Corridors (I RAIL)
€2.7m
CompletedFundación Valenciaport · Rail · Atlantic and Mediterranean · call 2018 · Jan 2019 → Dec 2023 · investment €6.9m
MedTIS III
€2.7m
CompletedAssociation des sociétés francaises d'autoroutes (ASFA) (Francia) · Road · Mediterranean Corridor · call 2016 · Feb 2017 → Dec 2021 · investment €13.5m
Mejora de las conexiones y el desarrollo de la Plataforma Logística Multimodal en el Puerto de Sevilla, el único puerto interior del sur de Europa.
€2.7m
CompletedAutoridad Portuaria de Sevilla · Multimodal · Mediterranean Corridor · call 2015 · Jan 2017 → Mar 2020 · investment €16.2m
Bridging Missing Links between FR&SP:Crossborder Railway Section Pau-Zaragoza. Somport Railway Tunnel Reopening
€2.5m
CompletedMinisterio de Fomento · Rail · Outside the corridors · call 2019 · Apr 2019 → Dec 2024 · investment €8.1m
Impulso de la energía combustibles sostenibles para el transporte de mercancías en las autopistas europeas (Bestway)
€2.5m
CompletedGas Natural Servicios SDG, SA · Road · Atlantic Corridor · call 2014 · Sept 2014 → Aug 2020 · investment €4.9m
Plataforma Intermodal Puerto de Huelva
€2.5m
CompletedAutoridad Portuaria de Huelva · Multimodal · Outside the corridors · call 2015 · Feb 2016 → Dec 2021 · investment €12.3m
Adaptation of Raíces Quay to new traffics
€2.3m
CompletedAutoridad Portuaria Avilés · Maritime · Outside the corridors · call 2019 · Apr 2019 → Dec 2024 · investment €11.4m
Estudio de demostración de la infraestructura asociada a una solución innovadora de tracción de gnl en la explotación ferroviaria
€2.3m
CompletedRENFE OPERADORA · Rail · Outside the corridors · call 2016 · Dec 2017 → Mar 2023 · investment €4.7m
Green and Connected Ports (GREEN C PORTS)
€2.3m
CompletedFundación Valenciaport · Maritime · Mediterranean Corridor · call 2018 · Apr 2019 → Mar 2023 · investment €4.6m
MedTIS II
€2.3m
CompletedAssociation professionnelle des societes francaises concessionnaires ou exploitantes deautoroutes ou deouvrages routiers (ASFA) · Road · Mediterranean Corridor · call 2014 · Jan 2014 → Dec 2018 · investment €11.5m
Preparatory Phase (Studies) for the optimization of the accessibility conditions to the Port of Seville
€2.2m
CompletedAutoridad Portuaria de Sevilla · Maritime · Outside the corridors · call 2020 · Apr 2021 → Dec 2024 · investment €4.3m
Bclink_MoS for the future
€2.1m
CompletedAutoritá di Sistema Portuale del Mar Tirreno Centro Settentrionale (Italia) · Maritime · Mediterranean Corridor · call 2017 · Jan 2018 → Dec 2024 · investment €14.2m
Enlace de enlaces faltantes entre FR&ES: estudios para la rehabilitación del tramo ferroviario transfronterizo Pau-Zaragoza
€2m
CompletedRégion Nouvelle-Aquitaine · Rail · Outside the corridors · call 2016 · Jul 2017 → Dec 2023 · investment €4m
BioLNG EuroNet
€2m
CompletedShell Western LNG B.V (Holanda) · Road · Atlantic and Mediterranean · call 2017 · Apr 2018 → Dec 2024 · investment €9.8m
LNGHIVE2 Vessels Demand2: Completing Green Links
€1.9m
CompletedBalèaria Eurolíneas Marítimas SA · Maritime · Mediterranean Corridor · call 2019 · Mar 2020 → Dec 2022 · investment €12.7m
Upgrading infrastructure at Seville Port to improve interconnection between the waterway and rail and maritime transport
€1.9m
CompletedAP SEVILLA · Multimodal · Atlantic and Mediterranean · call 2019 · Jul 2020 → Dec 2024 · investment €9.4m
EALINGWorks Valenciaport: Preparation of the electrical grid of the Port of Valencia for Onshore Power Supply
€1.8m
CompletedFUNDACIÓN VALENCIAPORT · Maritime · Mediterranean Corridor · call 2019 · Apr 2020 → Dec 2024 · investment €8.6m
Caresmatic - apoyo a la distribución de coches y coches eléctricos utilizando las soluciones de las autopistas del mar y promoviendo conceptos de transporte marítimo sostenible.
€1.7m
CompletedLuka Koper (Puerto de Koper) · Maritime · Mediterranean Corridor · call 2015 · Mar 2016 → Mar 2020 · investment €5.6m
Remodelación del complejo ferroviario de Chamartín en Madrid para adaptar los servicios de Alta Velocidad.
€1.6m
CompletedMinisterio de Fomento - Secretaria de Estado de Infraestructuras Transporte y Vivienda · Rail · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2020 · investment €3.2m
Proyecto CIRVE
€1.6m
CompletedIBIL Gestor de Carga del vehículo eléctrico S.A. · Road · Atlantic and Mediterranean · call 2015 · Jul 2016 → Dec 2021 · investment €3.2m
Accesibilidad universal en estaciones de pasajeros
€1.6m
CompletedADIF · Rail · Outside the corridors · call 2014 · Sept 2014 → Sept 2018 · investment €5.1m
Development of a network of alternative fuel technology in the Atlantic and Mediterranean corridors in Spain & Portugal
€1.5m
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLÍFEROS, S.A. (RCPP) · Road · Atlantic and Mediterranean · call 2019 · Jan 2021 → Dec 2024 · investment €10m
Grupo Ruiz Clean Bus Fleet
€1.5m
CompletedEmpresa Martín, S.A. · Road · Outside the corridors · call 2019 · Mar 2020 → Dec 2023 · investment €10.4m
Airis-ps. Implantación avanzada de los ris en el puerto de sevilla y guadalquivir euroway: la única vía navegable terrestre de españa en tent core netobra
€1.4m
CompletedAutoridad Portuaria de Sevilla · Inland waterways · Mediterranean Corridor · call 2015 · Jan 2017 → Apr 2021 · investment €2.9m
Development of LNG bunkering infrastructure in Bilbao, a strategic port in the North of Spain
€1.3m
CompletedRepsol LNG Holding S.A. · Maritime · Atlantic Corridor · call 2019 · Sept 2020 → Dec 2023 · investment €13.4m
Frigorail - Transporte ferroviario refrigerado entre España, Francia y Bélgica, utilizando corredores TEN-T
€1.3m
CompletedCOMSA RAIL TRANSPORT, SA · Rail · Mediterranean Corridor · call 2014 · Sept 2015 → Aug 2019 · investment €6.5m
Enlace Vial Transfronterizo en el Corredor Atlántico A25-IP5 Vilar Formoso - A-62 Fuentes de Oñoro
€1.3m
CompletedMinistério do Planeamiento e das Infraestruturas (Portugal) · Road · Atlantic Corridor · call 2016 · Feb 2017 → Jun 2021 · investment €12.9m
Rail connection to the outer port of the Port of Ferrol
€1.3m
CompletedAutoridad Portuaria Ferrol-San Cibrao · Maritime · Outside the corridors · call 2019 · Apr 2019 → Mar 2023 · investment €5.2m
Basic infrastructure to improve the commercial competitiveness and sustainability of the Port of Cartagena
€1.3m
CompletedAP CARTAGENA · Maritime · Outside the corridors · call 2020 · Mar 2021 → Dec 2024 · investment €2.5m
Chameleom. Creación de lng road haulage market de forma inteligente y rápida
€1.3m
CompletedHam Criogénica · Road · Mediterranean Corridor · call 2015 · Feb 2016 → Jun 2019 · investment €2.5m
ECO-Net_Spanish network of alternative fuels refuelling stations
€1.3m
CompletedENAGAS · Road · Atlantic and Mediterranean · call 2019 · Mar 2020 → Dec 2023 · investment €12.6m
A European FEderated Network of Information eXchange in Logistics (FENIX)
€1.3m
CompletedERTICO-ITS EUROPE (Bélgica) · Multimodal · Outside the corridors · call 2018 · Apr 2019 → Dec 2022 · investment €2.5m
IMAB. Interconexión de redes, puerto, aeropuerto y gestión óptima del tráfico en el área metropolitana de Barcelona, nodo del corredor europeo mediterráneo.
€1.3m
CompletedAyuntamiento Barcelona · Road · Mediterranean Corridor · call 2015 · Apr 2016 → Sept 2022 · investment €2.5m
Plan Director para el suministro de energía eléctrica a buques
€1.2m
CompletedPuertos del Estado · Maritime · Outside the corridors · call 2015 · Nov 2016 → Dec 2021 · investment €4.3m
Corredor Med / Atl. Tramo: Algeciras- Madrid - Zaragoza - Barcelona. Madrid- Vicálvaro actualización de la terminal ferroviaria de mercancías. Estudios. Fase 1.
€1.2m
CompletedADIF · Multimodal · Atlantic and Mediterranean · call 2014 · Jan 2016 → Dec 2018 · investment €2.4m
Despliegue avanzado de soluciones innovadoras para mejorar la gestión y operación del tráfico ferroviario en la red núcleo.
€1.2m
CompletedAutoridad Portuaria de Sevilla · Rail · Mediterranean Corridor · call 2016 · Sept 2017 → Dec 2021 · investment €2.4m
Variable Gauge for Freight Transport (Eje de Ancho Variable para Mercancías - EAVM)
€1.1m
CompletedADIF · Rail · Mediterranean Corridor · call 2018 · Nov 2018 → Jun 2021 · investment €2.3m
Entrega de carga con bajo nivel de ruido y baja emisión de carbono para los operadores postales para asegurar las conexiones de la última milla a través del transporte urbano y de larga distancia optimizado
€1m
CompletedSociedad Estatal Correos y Telégrafos, S.A. · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2020 · investment €2.1m
Estudios para el desarrollo de un terminal intermodal y área de actividad logística asociada (LAA de Murcia)
€970,450
CompletedConsejería de Fomento e Infraestructuras de la Región de Murcia (CARM) · Multimodal · Mediterranean Corridor · call 2014 · Jan 2015 → Dec 2022 · investment €1.9m
750-Meter Railway Sidings in Section Zaragoza- Barcelona of the Mediterranean Corridor. ZB750
€955,370
CompletedAutoridad Portuaria de Barcelona – Port de Barcelona · Rail · Outside the corridors · call 2020 · Apr 2021 → Dec 2024 · investment €1.9m
EALING - European flagship Action for coLd ironING in ports
€949,409
CompletedFUNDACIÓN VALENCIAPORT · Maritime · Outside the corridors · call 2019 · Jun 2020 → Jun 2023 · investment €1.9m
Application of Industry 4.0 Technologies towards Digital Port Container Terminals – iTerminals 4.0
€943,750
CompletedFundación Valenciaport · Maritime · Outside the corridors · call 2018 · Mar 2019 → Dec 2022 · investment €1.9m
SOLRED C-ITS Monitorización NetObra (SolC-ITS)
€905,500
CompletedSolred S.A. · Road · Outside the corridors · call 2015 · Mar 2016 → Apr 2020 · investment €1.8m
AIRIS II-SYNCHRO. Synchromodal Traffic & Transport Information Services
€850,000
CompletedAutoridad Portuaria Sevilla · Inland waterways · Mediterranean Corridor · call 2018 · May 2019 → Aug 2022 · investment €1.7m
CONCORDA
€817,500
CompletedERTICO- ITS Europe · Road · Outside the corridors · call 2016 · Oct 2017 → Jun 2021 · investment €1.6m
E-via - movilidad flex-e en at, de, es, fr, it
€811,575
CompletedENEL SpA (Italia) · Road · Atlantic and Mediterranean · call 2016 · Jul 2017 → Mar 2022 · investment €1.6m
Improvement of the railway connection with the port facilities located in Algeciras Bay
€806,945
CompletedAutoridad Portuaria de la Bahía de Algeciras · Multimodal · Outside the corridors · call 2020 · Aug 2021 → Dec 2024 · investment €1.6m
Arco atlántico fase III
€803,600
CompletedDepartment for Transport (UK) · Road · Atlantic Corridor · call 2016 · Mar 2017 → Dec 2021 · investment €4m
Autopista del ferrocarril del Atlántico: cambio modal de todo tipo de semirremolques en el corredor Atlántico
€762,500
CompletedMinistère de la Transition Écologique et Solidaire (MTES) · Multimodal · Atlantic Corridor · call 2016 · Feb 2017 → Mar 2024 · investment €1.5m
Parking seguros
€750,000
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLíFEROS S.A. · Road · Atlantic and Mediterranean · call 2014 · Jan 2014 → Dec 2017 · investment €1.5m
Estudio de los anchos de vía en los Corredores Ferroviarios para los servicios de "Autopistas Ferroviarias"
€750,000
CompletedADIF · Rail · Atlantic and Mediterranean · call 2016 · Jul 2017 → Dec 2023 · investment €1.5m
Nueva línea ferroviaria de alta capacidad: travesía central del Transpirineo. Estudios (Fase 2)
€750,000
CompletedAEIE TGC PIRINEOS · Rail · Outside the corridors · call 2014 · Mar 2016 → Jun 2020 · investment €1.5m
Autocits: regulación estudio de interoperabilidad en la adopción de la conducción autónoma en los nodos urbanos europeos
€737,700
CompletedIndra Sistemas, S.A. · Road · Outside the corridors · call 2015 · Nov 2016 → Mar 2019 · investment €1.5m
Prevención de incidentes y accidentes con embarcaciones más seguras en los océanos, PICASSO
€720,575
CompletedSASEMAR · Maritime · Outside the corridors · call 2015 · May 2016 → Jun 2018 · investment €1.4m
Installation of 160 High technology charging points (CPS) to boost electromobility in the Iberian Peninsula corridors
€706,500
CompletedEdp Comercial - Comercialização Energia, S. A · Road · Outside the corridors · call 2019 · Dec 2020 → Dec 2024 · investment €4.7m
Aplicación del programa de despliegue SESAR 2015 - grupo 1
€690,932
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2015 · Feb 2016 → Dec 2019 · investment €5.7m
Eliminación de cuellos de botella que impiden que el puerto de Cartagena conecte la red central y mejora el tráfico urbano (estudios)
€647,500
CompletedAutoridad Portuaria de Cartagena · Maritime · Mediterranean Corridor · call 2016 · Jan 2017 → Dec 2022 · investment €1.3m
Análisis de viabilidad sobre la armonización de las categorías de tipos de datos comunes para la red de carreteras y de transporte público (HARMONY)
€644,185
CompletedIndra Sistemas S.A · Multimodal · Outside the corridors · call 2014 · Nov 2015 → Dec 2018 · investment €1.3m
Vinculación Zaragoza: conectividad urbana con la red central.
€589,838
CompletedConsorcio de Transporte del Área de Zaragoza · Rail · Mediterranean Corridor · call 2016 · Feb 2017 → Aug 2019 · investment €1.2m
Apoyo a la implantación del ERTMS
€577,872
CompletedEEIG ERTMS Users Group · Rail · Outside the corridors · call 2014 · Jan 2015 → Dec 2017 · investment €1.2m
Línea de Bizkaia - Múltiples puertos Finlandia - Estonia - Bélgica - Servicio de larga distancia de España, relevante para muchos corredores de redes centrales
€571,500
CompletedFinnlines plc. · Maritime · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2016 · investment €1.9m
Acceso de calibre estándar entre la Plataforma Multimodal de La Llagosta y el Corredor Mediterráneo y adaptación a 750 metros de longitud. Estudios. Fase 1
€540,000
CompletedADIF · Multimodal · Mediterranean Corridor · call 2015 · Oct 2016 → Dec 2021 · investment €1.1m
I_HeERO
€535,478
CompletedNiedersachsisches Ministerium fur Wirtschaft, Arbeit und Verkehr (Germany) · Road · Outside the corridors · call 2014 · Jan 2015 → Mar 2018 · investment €1.1m
Corredor Atlántico / Mediterráneo. Nodo urbano de madrid. Estudios de adaptación mejorada e intermodal de la estación de Chamartín y acceso HSL al aeropuerto de Madrid.
€500,000
CompletedMinisterio de Fomento · Rail · Atlantic and Mediterranean · call 2015 · May 2016 → Jun 2019 · investment €1m
Despliegue de estaciones de autogás en diferentes áreas metropolitanas entre España y Portugal
€492,500
CompletedREPSOL BUTANO · Road · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2019 · investment €2.5m
Improvement of the Railway Interoperability and Connections with the hinterland of the Port of Huelva
€480,688
CompletedAutoridad Portuaria de Huelva · Multimodal · Outside the corridors · call 2020 · Apr 2021 → Dec 2024 · investment €961,376
Upgrading an old rail yard with a siding for trains with a length of 740 m in Ponferrada (Spain)
€415,000
CompletedAyuntamiento de Ponferrada, León, España. · Rail · Outside the corridors · call 2020 · Mar 2021 → Jul 2024 · investment €830,000
S/f samueLNG para un arco atlántico azul
€413,560
CompletedDragages Ports (Francia) · Maritime · Outside the corridors · call 2015 · Aug 2016 → Jun 2019 · investment €830,000
Mejora y fortalecimiento del Corredor de Carga Ferroviaria 6 - Corredor Mediterráneo, incluida la extensión a Croacia.
€400,000
CompletedGEIE per il Corridoio Merci 6 EEIG for Rail Freight Corridor 6 · Rail · Mediterranean Corridor · call 2014 · Jan 2015 → Dec 2018 · investment €800,000
Implementing Telematics Applications for European Interoperability
€278,340
CompletedRailNetEurope (Austria) · Rail · Outside the corridors · call 2018 · Jan 2019 → Dec 2023 · investment €560,000
Ecobono medatlántico
€271,340
CompletedPuertos del Estado · Maritime · Outside the corridors · call 2014 · Jul 2015 → Dec 2018 · investment €540,000
SCOOP@F Fase 2
€210,500
CompletedMinistere de l'ecologie, du developpement durable et de l'energie (MEDDE) · Road · Outside the corridors · call 2014 · Jan 2016 → Dec 2019 · investment €420,000
Saving lives assessing and improving TEN-t road networks safety
€191,000
CompletedEUROPEAN ROAD ASSESMENT ASSOCIATION (Bélgica) · Road · Outside the corridors · call 2018 · Apr 2019 → Jul 2021 · investment €380,000
Plataforma ITS europea
€180,500
CompletedMinistero delle Infrastrutture e dei Trasporti - Direzione territorio, la programmazione e i progetti internazionali · Road · Outside the corridors · call 2014 · Jul 2015 → Dec 2020 · investment €360,000
PRISME (PBN Regional Implementation and Sustained Monitoring of EGNOS Performance)
€179,401
CompletedPildo Consulting S.L. · Air · Outside the corridors · call 2017 · Sept 2018 → Jul 2022 · investment €360,000
SESAR Deployment Programme implementation 2016 – Cluster 2: Cohesion
€170,141
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2016 · Feb 2017 → Dec 2021 · investment €370,000
sAFE
€153,440
CompletedOECOM PRODUCT & SERVICES (Alemania) · Road · Outside the corridors · call 2018 · Jan 2019 → Dec 2021 · investment €310,000
Connect2LNG
€100,000
CompletedUnilever Poland Services Sp. Z.O.O. · Road · Atlantic Corridor · call 2014 · Oct 2015 → Dec 2018 · investment €200,000
Aplicación del programa de despliegue SESAR 2015 - grupo 3
€4,091
CompletedGestor Despliegue (ENAIRE) · Air · Outside the corridors · call 2015 · Feb 2016 → Feb 2022 · investment €10,000
Operaciones sostenibles de gnl para puertos y transporte marítimo - acciones piloto innovadoras
€1.3m
CompletedFundación Valenciaport · Maritime · Outside the corridors · call 2014 · Jan 2015 → Oct 2017
Nuevo acceso sur por ferrocarril y carretera al Puerto de Barcelona - Fase 2 - Obras de conexión.
€36.1m
TerminatedAutoridad Portuaria de Barcelona · Multimodal · Mediterranean Corridor · call 2014 · Jul 2015 → Dec 2018 · investment €120.4m
Línea ferroviaria de alta velocidad Bilbao-Vitoria (excluido acceso a la ciudad )
€21.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2016 → Dec 2019 · investment €105.7m
Despliegue de ERTMS (ETCS+GSMR) en el corredor atlántico. Tramo vitoria - bilbao - san sebastián
€11.7m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2015 · Aug 2017 → Dec 2020 · investment €23.3m
MiRO 2 - Multimodal Route connecting Barcelona to Paris
€11.1m
TerminatedVIIA (Francia) · Multimodal · Mediterranean Corridor · call 2018 · Feb 2019 → Dec 2023 · investment €55.4m
Tecnologías e innovación del gnl en el transporte marítimo para la promoción de la sostenibilidad, la multimodalidad y la eficiencia de la net obra (gainn 4 ship innovación)
€7.5m
TerminatedFundación Valenciaport · Maritime · Outside the corridors · call 2014 · Jan 2015 → Dec 2018 · investment €15m
LNGHIVE2 power supply & LNG bunkering
€6.4m
TerminatedSociedad de Gestión de Bienes de Equipos Eléctricos, S.L. · Maritime · Outside the corridors · call 2019 · Jan 2020 → Oct 2020 · investment €31.9m
Establishment of a new intermodal terminal at BASF ESPAÑOLA, S.L. in Tarragona - Spain - for modal shift between rail and road
€5.5m
TerminatedCOMBI TERMINAL CATALONIA, S.L. · Multimodal · Mediterranean Corridor · call 2014 · Oct 2015 → Sept 2019 · investment €25.5m
LNGHIVE2 FRS - PROMOTING ENERGY TRANSITION AND SUSTAINABLE TRANSPORT FREIGHT IN THE STRATEGICAL AREA OF GIBRALTAR STRAIT
€3m
TerminatedFörde Reederei Seetouristik Iberia S.L.U. · Maritime · Outside the corridors · call 2019 · Jan 2020 → Oct 2020 · investment €18m
Plataforma Logística Intermodal Constanti
€1.4m
TerminatedREPSOL QUíMICA S.A. · Rail · Mediterranean Corridor · call 2014 · Jun 2015 → Dec 2018 · investment €7m
Study for the optimization of an existing intermodal terminal in Port of Tarragona for modal shift between rail and road
€1.4m
TerminatedCOMBI TERMINAL CATALONIA SL · Multimodal · Outside the corridors · call 2020 · Mar 2021 → Jul 2024 · investment €2.7m
Corredor Atlántico / MED. Tren de alta velocidad Sines / Lisboa - Madrid. Nodo urbano de madrid. Estudio del Complejo Ferroviario de la Estación de Atocha (Fase 2).
€1.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2015 · Dec 2016 → Dec 2019 · investment €2.2m
Autopista del mar nantes saint nazaire - gijón
€1m
TerminatedAutoridad Portuaria de Gijón · Maritime · Outside the corridors · call 2015 · Feb 2016 → Dec 2018 · investment €3.4m
Blue gas growth to boost energy transition for low-carbon European economy (Blue2EU)
€930,000
TerminatedMOLGAS ENERGIA, S.A.U. · Road · Outside the corridors · call 2019 · investment €9.3m
Safe and Secure Parking Areas for Heavy-Duty Vehicles in Spanish Petrol Service Stations
€494,880
TerminatedREPSOL · Road · Atlantic and Mediterranean · call 2018 · Nov 2018 → Dec 2022 · investment €2.5m
H2Accelerate Expansion Network Part 2
—
TerminatedTotalenergies Marketing Services · Road · Outside the corridors · call CEF-T-2021-AFIFGEN-4.º corte
SESAR Deployment Programme implementation 2019 - IOP Foundation
€20m
TerminatedSESAR Deployment Alliance Association Internationale Sans But Lucratif · Air · Outside the corridors · call 2019 · Jan 2020 → Oct 2020 · investment €40m
MEDITERRANEAN CORRIDOR. SECTION CASTELLÓN-VANDELLÓS. IMPLEMENTATION OF UIC GAUGE. TRACK ASSEMBLAGE AND ELECTRIFICATION WORKS
—
TerminatedNo beneficiary · Rail · Outside the corridors · call CEF-T-2022-COREGEN
Road access to Intermodal Terminal and Logistic Activity Area of Murcia for its dual use
—
TerminatedCONSEJERIA DE FOMENTO E INFRAESTRUCTURAS · — · Outside the corridors · call CEF-T-2023-MILMOB
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.