Trans-European Network · Connecting Europe Facility
The CEF is the instrument the EU uses to pay for part of the works and studies on the TEN-T network. Here are all the projects with Spanish participation published by the Ministry: who receives them, in which corridor and how much Brussels contributes.
In less than a year, the Moon's shadow will sweep across southern Spain with over 4 minutes of total darkness over Algeciras, Tarifa, and Gibraltar.
CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
33 projects · funding €814.1m
Corredor atlántico: tramo Bergara-San Sebastián- Bayona. Estudios y obras y servicios de seguimiento de obras. Fase 1.
€448.1m
CompletedMinisterio de Fomento · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2023 · investment €1.1bn
Implementación del ancho UIC (fase 1) en el tramo Valencia-Tarragona-Barcelona del corredor Mediterráneo.
€124.5m
CompletedADIF · Rail · Mediterranean Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €311.2m
Implantacion del ancho UIC en el tramo Castellbisbal-Vilaseca. Corredor Mediterráneo.
€57m
CompletedADIF · Rail · Mediterranean Corridor · call 2017 · Jul 2017 → Dec 2024 · investment €285m
Mediterranean Corridor. Section Valencia-Sagunto-Castellón. Implementation of UIC gauge. Phase 2."
€41.5m
CompletedADIF · Rail · Mediterranean Corridor · call 2019 · Feb 2020 → Dec 2024 · investment €103.8m
Actualización y retroadaptación del ERTMS embarcado en los vehículos de renfe
€28m
CompletedRENFE F y M · Rail · Outside the corridors · call 2015 · Feb 2016 → Dec 2024 · investment €56m
Conexión ferroviaria Aveiro-Salamanca-Medina del Campo: obras en instalaciones y servicios de energía para trabajos de seguimiento.
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.
€19.6m
CompletedADIF · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €49m
Línea ferroviaria de alta velocidad Bilbao-Vitoria - Obras de plataforma en las subsecciones Elorroio-Atxondo y Atxondo-Abadino y trabajos de seguimiento.
€18.1m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · Dec 2015 → Dec 2020 · investment €90.4m
Corredor Atlántico. Suministro, instalaciones eléctricas y obras acústicas en la sección Chamartín-Atocha- Torrejón de Velasco del HSRL Madrid-Lisboa y Madrid- Bobadilla.
€11.4m
CompletedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2014 · May 2015 → Mar 2018 · investment €38.2m
Retroadaptación del ERTMS embarcado en los vehículos de renfe
€11.3m
CompletedRENFE-FABRICACIÓN Y MANTENIMIENTO SOCIEDAD MERCANTIL ESTATAL,S.A. · Rail · Outside the corridors · call 2016 · Feb 2017 → Dec 2024 · investment €22.5m
Despliegue de ERTMS en el tramo Valladolid-Burgos
€7.8m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2014 → Dec 2022 · investment €15.6m
Electrification and Signalling works in Crossborder Section Guillarei Tui
€6.5m
CompletedADIF · Rail · Outside the corridors · call 2019 · Sept 2019 → Dec 2023 · investment €16.3m
Atlantic Corridor. High Speed line Sines/Lisboa-Madrid. Madrid urban node. Study of the Railway Complex of Atocha Station (Phase 3)
€6m
CompletedADIF · Rail · Atlantic Corridor · call 2019 · Feb 2020 → Dec 2023 · investment €12m
Despliegue de ERTMS en las líneas de cercanías de Barcelona
€5.2m
CompletedADIF · Rail · Mediterranean Corridor · call 2014 · Nov 2015 → Dec 2022 · investment €10.4m
Actualización de todas las líneas de alta velocidad españolas a la versión 2.3.0.d. De ERTMS (ETCS+GSMR) 2ª fase
€4.2m
CompletedADIF · Rail · Outside the corridors · call 2014 · Apr 2014 → Jun 2022 · investment €8.4m
ATL_Freight_South_access_to_Bilbao_Port
€3.5m
CompletedDirección de Infraestructuras del Transporte. Gobierno Vasco · Rail · Outside the corridors · call 2020 · Mar 2021 → Dec 2024 · investment €7m
Interoperability of the rail system with TAF TSI in TEN-T Corridors (I RAIL)
€2.7m
CompletedFundación Valenciaport · Rail · Atlantic and Mediterranean · call 2018 · Jan 2019 → Dec 2023 · investment €6.9m
Bridging Missing Links between FR&SP:Crossborder Railway Section Pau-Zaragoza. Somport Railway Tunnel Reopening
€2.5m
CompletedMinisterio de Fomento · Rail · Outside the corridors · call 2019 · Apr 2019 → Dec 2024 · investment €8.1m
Estudio de demostración de la infraestructura asociada a una solución innovadora de tracción de gnl en la explotación ferroviaria
€2.3m
CompletedRENFE OPERADORA · Rail · Outside the corridors · call 2016 · Dec 2017 → Mar 2023 · investment €4.7m
Enlace de enlaces faltantes entre FR&ES: estudios para la rehabilitación del tramo ferroviario transfronterizo Pau-Zaragoza
€2m
CompletedRégion Nouvelle-Aquitaine · Rail · Outside the corridors · call 2016 · Jul 2017 → Dec 2023 · investment €4m
Remodelación del complejo ferroviario de Chamartín en Madrid para adaptar los servicios de Alta Velocidad.
€1.6m
CompletedMinisterio de Fomento - Secretaria de Estado de Infraestructuras Transporte y Vivienda · Rail · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2020 · investment €3.2m
Accesibilidad universal en estaciones de pasajeros
€1.6m
CompletedADIF · Rail · Outside the corridors · call 2014 · Sept 2014 → Sept 2018 · investment €5.1m
Frigorail - Transporte ferroviario refrigerado entre España, Francia y Bélgica, utilizando corredores TEN-T
€1.3m
CompletedCOMSA RAIL TRANSPORT, SA · Rail · Mediterranean Corridor · call 2014 · Sept 2015 → Aug 2019 · investment €6.5m
Despliegue avanzado de soluciones innovadoras para mejorar la gestión y operación del tráfico ferroviario en la red núcleo.
€1.2m
CompletedAutoridad Portuaria de Sevilla · Rail · Mediterranean Corridor · call 2016 · Sept 2017 → Dec 2021 · investment €2.4m
Variable Gauge for Freight Transport (Eje de Ancho Variable para Mercancías - EAVM)
€1.1m
CompletedADIF · Rail · Mediterranean Corridor · call 2018 · Nov 2018 → Jun 2021 · investment €2.3m
750-Meter Railway Sidings in Section Zaragoza- Barcelona of the Mediterranean Corridor. ZB750
€955,370
CompletedAutoridad Portuaria de Barcelona – Port de Barcelona · Rail · Outside the corridors · call 2020 · Apr 2021 → Dec 2024 · investment €1.9m
Nueva línea ferroviaria de alta capacidad: travesía central del Transpirineo. Estudios (Fase 2)
€750,000
CompletedAEIE TGC PIRINEOS · Rail · Outside the corridors · call 2014 · Mar 2016 → Jun 2020 · investment €1.5m
Estudio de los anchos de vía en los Corredores Ferroviarios para los servicios de "Autopistas Ferroviarias"
€750,000
CompletedADIF · Rail · Atlantic and Mediterranean · call 2016 · Jul 2017 → Dec 2023 · investment €1.5m
Vinculación Zaragoza: conectividad urbana con la red central.
€589,838
CompletedConsorcio de Transporte del Área de Zaragoza · Rail · Mediterranean Corridor · call 2016 · Feb 2017 → Aug 2019 · investment €1.2m
Apoyo a la implantación del ERTMS
€577,872
CompletedEEIG ERTMS Users Group · Rail · Outside the corridors · call 2014 · Jan 2015 → Dec 2017 · investment €1.2m
Corredor Atlántico / Mediterráneo. Nodo urbano de madrid. Estudios de adaptación mejorada e intermodal de la estación de Chamartín y acceso HSL al aeropuerto de Madrid.
€500,000
CompletedMinisterio de Fomento · Rail · Atlantic and Mediterranean · call 2015 · May 2016 → Jun 2019 · investment €1m
Upgrading an old rail yard with a siding for trains with a length of 740 m in Ponferrada (Spain)
€415,000
CompletedAyuntamiento de Ponferrada, León, España. · Rail · Outside the corridors · call 2020 · Mar 2021 → Jul 2024 · investment €830,000
Mejora y fortalecimiento del Corredor de Carga Ferroviaria 6 - Corredor Mediterráneo, incluida la extensión a Croacia.
€400,000
CompletedGEIE per il Corridoio Merci 6 EEIG for Rail Freight Corridor 6 · Rail · Mediterranean Corridor · call 2014 · Jan 2015 → Dec 2018 · investment €800,000
Implementing Telematics Applications for European Interoperability
€278,340
CompletedRailNetEurope (Austria) · Rail · Outside the corridors · call 2018 · Jan 2019 → Dec 2023 · investment €560,000