Loading data…
Trans-European Network · Connecting Europe Facility
The CEF is the instrument the EU uses to pay for part of the works and studies on the TEN-T network. Here are all the projects with Spanish participation published by the Ministry: who receives them, in which corridor and how much Brussels contributes.
In less than a year, the Moon's shadow will sweep across southern Spain with over 4 minutes of total darkness over Algeciras, Tarifa, and Gibraltar.
CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
8 projects · funding €18m
Estudios y obras para conexiones por ferrocarril de 4 terminales de carga existentes a lo largo del Corredor Mediterráneo en España por GRUPO ALONSO
€5.2m
CompletedServicios Terrestres y Marítimos S.A. (Grupo ALONSO) · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2022 · investment €21.1m
Madrid Vicálvaro Freight Railway Terminal.Works Phase 1.Subphase 1A. Mediterranean Corridor. Rail Works and Road Studies
€4.5m
CompletedADIF · Multimodal · Mediterranean Corridor · call 2018 · Nov 2018 → Dec 2023 · investment €21.1m
Mejora de las conexiones y el desarrollo de la Plataforma Logística Multimodal en el Puerto de Sevilla, el único puerto interior del sur de Europa.
€2.7m
CompletedAutoridad Portuaria de Sevilla · Multimodal · Mediterranean Corridor · call 2015 · Jan 2017 → Mar 2020 · investment €16.2m
Upgrading infrastructure at Seville Port to improve interconnection between the waterway and rail and maritime transport
€1.9m
CompletedAP SEVILLA · Multimodal · Atlantic and Mediterranean · call 2019 · Jul 2020 → Dec 2024 · investment €9.4m
Corredor Med / Atl. Tramo: Algeciras- Madrid - Zaragoza - Barcelona. Madrid- Vicálvaro actualización de la terminal ferroviaria de mercancías. Estudios. Fase 1.
€1.2m
ADIF · Multimodal · Atlantic and Mediterranean · call 2014 · Jan 2016 → Dec 2018 · investment €2.4m
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.
Entrega de carga con bajo nivel de ruido y baja emisión de carbono para los operadores postales para asegurar las conexiones de la última milla a través del transporte urbano y de larga distancia optimizado
€1m
CompletedSociedad Estatal Correos y Telégrafos, S.A. · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2020 · investment €2.1m
Estudios para el desarrollo de un terminal intermodal y área de actividad logística asociada (LAA de Murcia)
€970,450
CompletedConsejería de Fomento e Infraestructuras de la Región de Murcia (CARM) · Multimodal · Mediterranean Corridor · call 2014 · Jan 2015 → Dec 2022 · investment €1.9m
Acceso de calibre estándar entre la Plataforma Multimodal de La Llagosta y el Corredor Mediterráneo y adaptación a 750 metros de longitud. Estudios. Fase 1
€540,000
CompletedADIF · Multimodal · Mediterranean Corridor · call 2015 · Oct 2016 → Dec 2021 · investment €1.1m