Loading data…
Trans-European Network · Connecting Europe Facility
The CEF is the instrument the EU uses to pay for part of the works and studies on the TEN-T network. Here are all the projects with Spanish participation published by the Ministry: who receives them, in which corridor and how much Brussels contributes.
In less than a year, the Moon's shadow will sweep across southern Spain with over 4 minutes of total darkness over Algeciras, Tarifa, and Gibraltar.
CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
78 projects · funding €1.2bn
ATLANTIC CORRIDOR: SECTION BERGARA-SAN SEBASTIAN-BAYONNE. BERGARA JUNCTION TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. PHASE 2
€145.4m
OngoingADIF Alta Velocidad · Rail · Atlantic Corridor · call CEF-T-2021-COREGEN · Jan 2021 → Dec 2025 · investment €290.8m
TANGERINE
€40.6m
OngoingIberdrola Clientes SA (IBCLI) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €40.6m
Accelerate Europe’s key infrastructure - GENERAL
€23.4m
OngoingTesla Italy SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €23.4m
PALLANTIA
€22.5m
OngoingGrupo Easycharger SA · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €22.5m
ATLANTIC CORRIDOR. TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. SECTION ATXONDO - ABADIÑO. PHASE 2
€22m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-COREGEN · Feb 2023 → Jan 2027 · investment €73.4m
PALMAS PORT SPHINX DIKE PHASE IV
€20.6m
OngoingA.P. Las Palmas · Maritime · Atlantic Corridor · call CEF-T-2021-COREGEN · Mar 2021 → Jul 2025 · investment €29.5m
CADIZ CONTAINER MULTIMODAL TERMINAL AND LAND ACCESS. PHASE II
€15.6m
OngoingAutoridad Portuaria de la Bahía de Cádiz · Maritime · Atlantic Corridor · call CEF-T-2021-COMPGEN · Oct 2022 → Jun 2026 · investment €52.1m
Smart Electrification Infrastructure for the Urban Surface
€15.4m
OngoingEMT · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €51.2m
Bilbao Port Net-Zero Green Onshore Power System for Comprehensive Support & Core TEN-T Cold Ironing Capabilities Expansion in the Atlantic Corridor
€14.3m
OngoingAutoridad Portuaria de Bilbao · Maritime · Atlantic Corridor · call CEF-T-2021-COREGEN · Feb 2022 → Jan 2026 · investment €47.5m
HY2MOVE1
€12.8m
OngoingRepsol Comercial de Productos Petrolíferos (RCPP) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Dec 2022 → Oct 2025 · investment €42.8m
Accelerating on-the-go EV ultra-fast charging network in Italy, France, Spain and Portugal
€11.4m
OngoingAtlante SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Apr 2026 · investment €11.4m
2023 Arnedo Secure Ecopark
€7.9m
OngoingINMO-ARNEDO S.L.U · Road · Atlantic Corridor · call CEF-T-2023 · Oct 2024 → Mar 2026 · investment €18.5m
INSPIRA MADRID
€7.4m
OngoingFRV-X · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €24.6m
Mediterranean-Atlantic Transport Intelligent Systems
€6.7m
OngoingASFA · Road · Atlantic and Mediterranean · call CEF-T-2022-SIMOBGEN · Jan 2023 → Jan 2027 · investment €13.5m
Intermodal Platform of the Port of Huelva II: a boost to multimodality, connectivity and sustainability
€6.7m
OngoingAutoridad Portuaria de Huelva · Multimodal · Atlantic Corridor · call CEF-T-2022-COREGEN · Oct 2022 → Apr 2025 · investment €22.4m
Design and deployment of On-shore powersupply in Algeciras Port
€6.4m
OngoingAP BAHIA DE ALGECIRAS · Maritime · Atlantic and Mediterranean · call CEF-T-2022-COREGEN · Mar 2023 → Jan 2027 · investment €20.3m
Next Wav-E: Developing an EU-wide network of electric vehicles’ high-power charging infrastructure for the electrification of mobility and decarbonisation of the road transport sector
€6m
OngoingENEL X WAY · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Nov 2022 → Nov 2025 · investment €6m
Southern European EV fast-charging network (Italy, France, Spain)
€5.8m
OngoingAtlante SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025 · investment €5.8m
Port Real-time Information Smart Management; PRISMA
€5.1m
OngoingAUTORIDAD PORTUARIA DE SEVILLA · Maritime · Atlantic and Mediterranean · call CEF-T-2023 · Jan 2024 → Dec 2027 · investment €10.3m
Improvements on the road access to the maritime port of Bilbao and its connectivity with other critical infrastructures in the Biscay region
€5.1m
OngoingDIPUTACION FORAL DE BIZKAIA · Road · Atlantic Corridor · call CEF-T-2022-MILMOB · Sept 2022 → Mar 2026 · investment €10.2m
Ultrafast e-mobility infrastructure in ES-PT Mediterranean
€4.5m
OngoingCEPSA COMERCIAL PETROLEO SA (CCP) · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €4.5m
Works for basic maritime infrastructures, heel and RO-RO ramp, at Raos 9 quay to improve the efficiency of the port of Santander (Cantabria)
€3.5m
OngoingAUTORIDAD PORTUARIA DE SANTANDER · Maritime · Atlantic Corridor · call CEF-T-2023 · Aug 2024 → Jan 2026 · investment €11.9m
Spanish Airports' decarbonization through the implementation of electric vehicles of handling operators
€3.4m
OngoingAENA SME SA · Air · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Apr 2023 → Dec 2024 · investment €11.3m
Spanish Safe and Secure Truck Parking Area Network
€3.1m
OngoingGP Límite Andamur SL · Road · Atlantic and Mediterranean · call CEF-T-2021-SAFEMOBGEN · Mar 2022 → Sept 2025 · investment €6.3m
Heavy Wav-E, Mediterranean ultra-fast charging arteria for electric heavy-duty and light-duty vehicles
€2.8m
OngoingENEL X WAY · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-4.º corte · Jul 2023 → Dec 2025 · investment €2.8m
European flagship action for cold ironing Works in Gijon Port
€2.6m
OngoingAUTORIDAD PORTUARIA DE GIJON · Maritime · Atlantic Corridor · call CEF-T-2023 · Oct 2024 → Dec 2027 · investment €8.6m
Safe and secure parking area in Pinto in the South of Madrid on the Atlantic TEN-T Core Network Corridor
€2.4m
OngoingAtalaya Patrimonio Inmobiliario S.L · Road · Atlantic and Mediterranean · call CEF-T-2023 · Sept 2024 → Oct 2025 · investment €4.9m
Study of gauges for the development of Rail Motorway Algeciras - Zaragoza
€2.4m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.9m
Works for gauge adaptation in railway line Medina del Campo – Salamanca- Fuentes de Oñoro and services to follow-up works
€2.2m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.5m
Accelerating Europe’s key infrastructure phase II
€1.8m
OngoingTesla Motors Netherlands B.V · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-5.º corte · Nov 2023 → Nov 2026 · investment €1.8m
Desarrollo del Corredor de Carga Ferroviaria Atlántico "Sines-Lisboa / Leixoes - Madrid- Medina del Campo / Bilbao / San Sebastián-Irún-Burdeos-París / Le Havre / Metz - Estrasburgo / Mannheim / Sines-Elvas / Algeciras"
€765,000
OngoingGEIE Corridor Ferroviaire de Marchandises 4 (GEIE CFM4) · Rail · Atlantic Corridor · call 2014 · Nov 2015 → Mar 2021 · investment €1.5m
AMBRA-E lectrify Europe
€14.2m
OngoingEnel X S.r.l. (Italia) · Road · Atlantic and Mediterranean · call 2017 · Sept 2018 → Dec 2022
European Hydrogen Network by Hype
€18.1m
OngoingHype Assets · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-3er. corte · Nov 2022 → Nov 2025
Expand-E General: EXpanding Performance and Network Density – Electric
€28.2m
OngoingIONITY GMBH · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025
Ultra Fast in Europe
€50.4m
OngoingBE CHARGE SRL · Road · Atlantic and Mediterranean · call CEF-T-2021-AFIFGEN-2.º corte · Jun 2022 → Jun 2025
Corredor atlántico: tramo Bergara-San Sebastián- Bayona. Estudios y obras y servicios de seguimiento de obras. Fase 1.
€448.1m
CompletedMinisterio de Fomento · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2023 · investment €1.1bn
Pruebas futuras del Puerto de Bilbao perteneciente a la red básica del corredor atlántico.
€23.2m
CompletedAutoridad Portuaria de Bilbao · Maritime · Atlantic Corridor · call 2014 · Jan 2015 → Oct 2021 · investment €116.2m
Conexión ferroviaria Aveiro-Salamanca-Medina del Campo: obras en instalaciones y servicios de energía para trabajos de seguimiento.
€19.6m
CompletedADIF · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €49m
Línea ferroviaria de alta velocidad Bilbao-Vitoria - Obras de plataforma en las subsecciones Elorroio-Atxondo y Atxondo-Abadino y trabajos de seguimiento.
€18.1m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · Dec 2015 → Dec 2020 · investment €90.4m
IBERDROLA SMART MOBILITY
€13.4m
CompletedIBERDROLA CLIENTES, S.A. · Road · Atlantic and Mediterranean · call 2019 · Mar 2020 → Dec 2022 · investment €89.2m
LNGHIVE2 VESSEL DEMAND: GREEN AND SMART LINKS
€11.8m
CompletedBalearia · Maritime · Atlantic and Mediterranean · call 2017 · Apr 2018 → Jul 2021 · investment €59m
Corredor Atlántico. Suministro, instalaciones eléctricas y obras acústicas en la sección Chamartín-Atocha- Torrejón de Velasco del HSRL Madrid-Lisboa y Madrid- Bobadilla.
€11.4m
CompletedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2014 · May 2015 → Mar 2018 · investment €38.2m
LNGHIVE2 Algeciras - A Flex LNG bunkering facility in the port of Algeciras Bay
€11.3m
CompletedENAGAS · Maritime · Atlantic and Mediterranean · call 2019 · Jul 2020 → May 2023 · investment €56.5m
Despliegue de ERTMS en el tramo Valladolid-Burgos
€7.8m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2014 → Dec 2022 · investment €15.6m
Plataforma logística intermodal en el suroeste de Europa
€7.6m
CompletedGobierno de Extremadura · Multimodal · Atlantic Corridor · call 2014 · Apr 2014 → Sept 2022 · investment €35.8m
Project Everest
€7.3m
CompletedNORDIAN CPO, SL · Road · Atlantic and Mediterranean · call 2019 · Aug 2020 → Jun 2023 · investment €48.9m
Atlantic Corridor. High Speed line Sines/Lisboa-Madrid. Madrid urban node. Study of the Railway Complex of Atocha Station (Phase 3)
€6m
CompletedADIF · Rail · Atlantic Corridor · call 2019 · Feb 2020 → Dec 2023 · investment €12m
Estudios y obras para conexiones por ferrocarril de 4 terminales de carga existentes a lo largo del Corredor Mediterráneo en España por GRUPO ALONSO
€5.2m
CompletedServicios Terrestres y Marítimos S.A. (Grupo ALONSO) · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2022 · investment €21.1m
Eco-gate: corredores europeos para la eficiencia del transporte de gas natural
€5.1m
CompletedGas Natural Madrid SDG, S.A. · Road · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2021 · investment €10.2m
Development of a network of alternative fuel technology in the Atlantic and Mediterranean corridors across Spain
€3.3m
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLÍFEROS, S.A. (RCPP) · Road · Atlantic and Mediterranean · call 2019 · Jul 2020 → Dec 2024 · investment €21.9m
Arco atlantico fase II
€3m
CompletedDepartment for Transport UK · Road · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2017 · investment €14.8m
LNGHIVE2 INFRASTRUCTURE AND LOGISTICS SOLUTIONS
€2.9m
CompletedEnagas Transporte, S.A.U. · Maritime · Atlantic and Mediterranean · call 2017 · Sept 2018 → Dec 2023 · investment €14.7m
Setting up two safe and secure parking areas in the Spanish-French border region
€2.8m
CompletedAgencia Guipuzcoana de lnfraestructuras S.A. (BIDEGI S.A.) · Road · Atlantic Corridor · call 2019 · Feb 2020 → Oct 2020 · investment €15.2m
Interoperability of the rail system with TAF TSI in TEN-T Corridors (I RAIL)
€2.7m
CompletedFundación Valenciaport · Rail · Atlantic and Mediterranean · call 2018 · Jan 2019 → Dec 2023 · investment €6.9m
Impulso de la energía combustibles sostenibles para el transporte de mercancías en las autopistas europeas (Bestway)
€2.5m
CompletedGas Natural Servicios SDG, SA · Road · Atlantic Corridor · call 2014 · Sept 2014 → Aug 2020 · investment €4.9m
BioLNG EuroNet
€2m
CompletedShell Western LNG B.V (Holanda) · Road · Atlantic and Mediterranean · call 2017 · Apr 2018 → Dec 2024 · investment €9.8m
Upgrading infrastructure at Seville Port to improve interconnection between the waterway and rail and maritime transport
€1.9m
CompletedAP SEVILLA · Multimodal · Atlantic and Mediterranean · call 2019 · Jul 2020 → Dec 2024 · investment €9.4m
Remodelación del complejo ferroviario de Chamartín en Madrid para adaptar los servicios de Alta Velocidad.
€1.6m
CompletedMinisterio de Fomento - Secretaria de Estado de Infraestructuras Transporte y Vivienda · Rail · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2020 · investment €3.2m
Proyecto CIRVE
€1.6m
CompletedIBIL Gestor de Carga del vehículo eléctrico S.A. · Road · Atlantic and Mediterranean · call 2015 · Jul 2016 → Dec 2021 · investment €3.2m
Development of a network of alternative fuel technology in the Atlantic and Mediterranean corridors in Spain & Portugal
€1.5m
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLÍFEROS, S.A. (RCPP) · Road · Atlantic and Mediterranean · call 2019 · Jan 2021 → Dec 2024 · investment €10m
Development of LNG bunkering infrastructure in Bilbao, a strategic port in the North of Spain
€1.3m
CompletedRepsol LNG Holding S.A. · Maritime · Atlantic Corridor · call 2019 · Sept 2020 → Dec 2023 · investment €13.4m
Enlace Vial Transfronterizo en el Corredor Atlántico A25-IP5 Vilar Formoso - A-62 Fuentes de Oñoro
€1.3m
CompletedMinistério do Planeamiento e das Infraestruturas (Portugal) · Road · Atlantic Corridor · call 2016 · Feb 2017 → Jun 2021 · investment €12.9m
ECO-Net_Spanish network of alternative fuels refuelling stations
€1.3m
CompletedENAGAS · Road · Atlantic and Mediterranean · call 2019 · Mar 2020 → Dec 2023 · investment €12.6m
Corredor Med / Atl. Tramo: Algeciras- Madrid - Zaragoza - Barcelona. Madrid- Vicálvaro actualización de la terminal ferroviaria de mercancías. Estudios. Fase 1.
€1.2m
CompletedADIF · Multimodal · Atlantic and Mediterranean · call 2014 · Jan 2016 → Dec 2018 · investment €2.4m
Entrega de carga con bajo nivel de ruido y baja emisión de carbono para los operadores postales para asegurar las conexiones de la última milla a través del transporte urbano y de larga distancia optimizado
€1m
CompletedSociedad Estatal Correos y Telégrafos, S.A. · Multimodal · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2020 · investment €2.1m
E-via - movilidad flex-e en at, de, es, fr, it
€811,575
CompletedENEL SpA (Italia) · Road · Atlantic and Mediterranean · call 2016 · Jul 2017 → Mar 2022 · investment €1.6m
Arco atlántico fase III
€803,600
CompletedDepartment for Transport (UK) · Road · Atlantic Corridor · call 2016 · Mar 2017 → Dec 2021 · investment €4m
Autopista del ferrocarril del Atlántico: cambio modal de todo tipo de semirremolques en el corredor Atlántico
€762,500
CompletedMinistère de la Transition Écologique et Solidaire (MTES) · Multimodal · Atlantic Corridor · call 2016 · Feb 2017 → Mar 2024 · investment €1.5m
Estudio de los anchos de vía en los Corredores Ferroviarios para los servicios de "Autopistas Ferroviarias"
€750,000
CompletedADIF · Rail · Atlantic and Mediterranean · call 2016 · Jul 2017 → Dec 2023 · investment €1.5m
Parking seguros
€750,000
CompletedREPSOL COMERCIAL DE PRODUCTOS PETROLíFEROS S.A. · Road · Atlantic and Mediterranean · call 2014 · Jan 2014 → Dec 2017 · investment €1.5m
Línea de Bizkaia - Múltiples puertos Finlandia - Estonia - Bélgica - Servicio de larga distancia de España, relevante para muchos corredores de redes centrales
€571,500
CompletedFinnlines plc. · Maritime · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2016 · investment €1.9m
Corredor Atlántico / Mediterráneo. Nodo urbano de madrid. Estudios de adaptación mejorada e intermodal de la estación de Chamartín y acceso HSL al aeropuerto de Madrid.
€500,000
CompletedMinisterio de Fomento · Rail · Atlantic and Mediterranean · call 2015 · May 2016 → Jun 2019 · investment €1m
Despliegue de estaciones de autogás en diferentes áreas metropolitanas entre España y Portugal
€492,500
CompletedREPSOL BUTANO · Road · Atlantic and Mediterranean · call 2015 · Feb 2016 → Dec 2019 · investment €2.5m
Connect2LNG
€100,000
CompletedUnilever Poland Services Sp. Z.O.O. · Road · Atlantic Corridor · call 2014 · Oct 2015 → Dec 2018 · investment €200,000
Línea ferroviaria de alta velocidad Bilbao-Vitoria (excluido acceso a la ciudad )
€21.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2016 → Dec 2019 · investment €105.7m
Despliegue de ERTMS (ETCS+GSMR) en el corredor atlántico. Tramo vitoria - bilbao - san sebastián
€11.7m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2015 · Aug 2017 → Dec 2020 · investment €23.3m
Corredor Atlántico / MED. Tren de alta velocidad Sines / Lisboa - Madrid. Nodo urbano de madrid. Estudio del Complejo Ferroviario de la Estación de Atocha (Fase 2).
€1.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2015 · Dec 2016 → Dec 2019 · investment €2.2m
Safe and Secure Parking Areas for Heavy-Duty Vehicles in Spanish Petrol Service Stations
€494,880
TerminatedREPSOL · Road · Atlantic and Mediterranean · call 2018 · Nov 2018 → Dec 2022 · investment €2.5m
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.