Trans-European Network · Connecting Europe Facility
The CEF is the instrument the EU uses to pay for part of the works and studies on the TEN-T network. Here are all the projects with Spanish participation published by the Ministry: who receives them, in which corridor and how much Brussels contributes.
In less than a year, the Moon's shadow will sweep across southern Spain with over 4 minutes of total darkness over Algeciras, Tarifa, and Gibraltar.
CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
18 projects · funding €723.3m
ATLANTIC CORRIDOR: SECTION BERGARA-SAN SEBASTIAN-BAYONNE. BERGARA JUNCTION TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. PHASE 2
€145.4m
OngoingADIF Alta Velocidad · Rail · Atlantic Corridor · call CEF-T-2021-COREGEN · Jan 2021 → Dec 2025 · investment €290.8m
ATLANTIC CORRIDOR. TRACK BED WORKS AND SERVICES FOR FOLLOW-UP WORKS. SECTION ATXONDO - ABADIÑO. PHASE 2
€22m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-COREGEN · Feb 2023 → Jan 2027 · investment €73.4m
Study of gauges for the development of Rail Motorway Algeciras - Zaragoza
€2.4m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.9m
Works for gauge adaptation in railway line Medina del Campo – Salamanca- Fuentes de Oñoro and services to follow-up works
€2.2m
OngoingADIF · Rail · Atlantic Corridor · call CEF-T-2022-MILMOB · Oct 2022 → Dec 2025 · investment €4.5m
Desarrollo del Corredor de Carga Ferroviaria Atlántico "Sines-Lisboa / Leixoes - Madrid- Medina del Campo / Bilbao / San Sebastián-Irún-Burdeos-París / Le Havre / Metz - Estrasburgo / Mannheim / Sines-Elvas / Algeciras"
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.
€765,000
OngoingGEIE Corridor Ferroviaire de Marchandises 4 (GEIE CFM4) · Rail · Atlantic Corridor · call 2014 · Nov 2015 → Mar 2021 · investment €1.5m
Corredor atlántico: tramo Bergara-San Sebastián- Bayona. Estudios y obras y servicios de seguimiento de obras. Fase 1.
€448.1m
CompletedMinisterio de Fomento · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2023 · investment €1.1bn
Conexión ferroviaria Aveiro-Salamanca-Medina del Campo: obras en instalaciones y servicios de energía para trabajos de seguimiento.
€19.6m
CompletedADIF · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €49m
Línea ferroviaria de alta velocidad Bilbao-Vitoria - Obras de plataforma en las subsecciones Elorroio-Atxondo y Atxondo-Abadino y trabajos de seguimiento.
€18.1m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · Dec 2015 → Dec 2020 · investment €90.4m
Corredor Atlántico. Suministro, instalaciones eléctricas y obras acústicas en la sección Chamartín-Atocha- Torrejón de Velasco del HSRL Madrid-Lisboa y Madrid- Bobadilla.
€11.4m
CompletedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2014 · May 2015 → Mar 2018 · investment €38.2m
Despliegue de ERTMS en el tramo Valladolid-Burgos
€7.8m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2014 → Dec 2022 · investment €15.6m
Atlantic Corridor. High Speed line Sines/Lisboa-Madrid. Madrid urban node. Study of the Railway Complex of Atocha Station (Phase 3)
€6m
CompletedADIF · Rail · Atlantic Corridor · call 2019 · Feb 2020 → Dec 2023 · investment €12m
Interoperability of the rail system with TAF TSI in TEN-T Corridors (I RAIL)
€2.7m
CompletedFundación Valenciaport · Rail · Atlantic and Mediterranean · call 2018 · Jan 2019 → Dec 2023 · investment €6.9m
Remodelación del complejo ferroviario de Chamartín en Madrid para adaptar los servicios de Alta Velocidad.
€1.6m
CompletedMinisterio de Fomento - Secretaria de Estado de Infraestructuras Transporte y Vivienda · Rail · Atlantic and Mediterranean · call 2016 · Feb 2017 → Dec 2020 · investment €3.2m
Estudio de los anchos de vía en los Corredores Ferroviarios para los servicios de "Autopistas Ferroviarias"
€750,000
CompletedADIF · Rail · Atlantic and Mediterranean · call 2016 · Jul 2017 → Dec 2023 · investment €1.5m
Corredor Atlántico / Mediterráneo. Nodo urbano de madrid. Estudios de adaptación mejorada e intermodal de la estación de Chamartín y acceso HSL al aeropuerto de Madrid.
€500,000
CompletedMinisterio de Fomento · Rail · Atlantic and Mediterranean · call 2015 · May 2016 → Jun 2019 · investment €1m
Línea ferroviaria de alta velocidad Bilbao-Vitoria (excluido acceso a la ciudad )
€21.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2016 → Dec 2019 · investment €105.7m
Despliegue de ERTMS (ETCS+GSMR) en el corredor atlántico. Tramo vitoria - bilbao - san sebastián
€11.7m
TerminatedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2015 · Aug 2017 → Dec 2020 · investment €23.3m
Corredor Atlántico / MED. Tren de alta velocidad Sines / Lisboa - Madrid. Nodo urbano de madrid. Estudio del Complejo Ferroviario de la Estación de Atocha (Fase 2).
€1.1m
TerminatedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2015 · Dec 2016 → Dec 2019 · investment €2.2m