CEF funding awarded
€2.5bn
Total investment mobilised
€6.4bn
Ongoing projects
68
Largest beneficiary
€451.1m
Where they are
Who receives the most
- 01Ministerio de Fomento3€451.1m
- 02ADIF17€300.9m
- 03Gestor Despliegue (ENAIRE)7€280.3m
- 04ADIF Alta Velocidad7€216.6m
- 05ADMINISTRADOR DE INFRAESTRUCTURAS FERROVIARIAS1€77.8m
- 06BE CHARGE SRL1€50.4m
- 07Iberdrola Clientes SA (IBCLI)1€40.6m
- 08European High Power Charging Beteiligungsgesellschaft mbH1€39.1m
- 09ENAIRE2€37.7m
- 10Autoridad Portuaria de Bilbao2€37.5m
By status
- Completed 127€1.4bn
- Ongoing 68€870.7m
- Terminated 18€128.7m
- In preparation 8€72.7m
By mode
- Rail 47€1.1bn
- Road 74€469.3m
- Air 19€372.7m
- Maritime 49€301m
- Multimodal 29€180.8m
- Inland waterways 2€2.3m
- No mode 1€0
By corridor
- Atlantic Corridor 31€825.4m
- Outside the corridors 97€691.2m
- Mediterranean Corridor 46€558.3m
- Atlantic and Mediterranean 47€384m
Projects · “ADIF”
7 projects · funding €64.9m
Conexión ferroviaria Aveiro-Salamanca-Medina del Campo: obras en instalaciones y servicios de energía para trabajos de seguimiento.
€19.6m
CompletedADIF · Rail · Atlantic Corridor · call 2014 · Jan 2014 → Dec 2022 · investment €49m
Línea ferroviaria de alta velocidad Bilbao-Vitoria - Obras de plataforma en las subsecciones Elorroio-Atxondo y Atxondo-Abadino y trabajos de seguimiento.
€18.1m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · Dec 2015 → Dec 2020 · investment €90.4m
Corredor Atlántico. Suministro, instalaciones eléctricas y obras acústicas en la sección Chamartín-Atocha- Torrejón de Velasco del HSRL Madrid-Lisboa y Madrid- Bobadilla.
€11.4m
CompletedADIF Alta Velocidad · Rail · Atlantic and Mediterranean · call 2014 · May 2015 → Mar 2018 · investment €38.2m
Despliegue de ERTMS en el tramo Valladolid-Burgos
€7.8m
CompletedADIF Alta Velocidad · Rail · Atlantic Corridor · call 2014 · May 2014 → Dec 2022 · investment €15.6m
Atlantic Corridor. High Speed line Sines/Lisboa-Madrid. Madrid urban node. Study of the Railway Complex of Atocha Station (Phase 3)
€6m
CompletedADIF · Rail · Atlantic Corridor · call 2019 · Feb 2020 → Dec 2023 · investment €12m
Corredor Med / Atl. Tramo: Algeciras- Madrid - Zaragoza - Barcelona. Madrid- Vicálvaro actualización de la terminal ferroviaria de mercancías. Estudios. Fase 1.
€1.2m
CompletedADIF · Multimodal · Atlantic and Mediterranean · call 2014 · Jan 2016 → Dec 2018 · investment €2.4m
Estudio de los anchos de vía en los Corredores Ferroviarios para los servicios de "Autopistas Ferroviarias"
€750,000
CompletedADIF · Rail · Atlantic and Mediterranean · call 2016 · Jul 2017 → Dec 2023 · investment €1.5m
“Funding” is the CEF grant awarded to the Spanish part of each action; “investment” is the total cost of that part. A single European project may be split across several countries: only the Spanish share appears here. Status as reported by the Ministry: ongoing, completed, terminated or in preparation. Project titles are the EU’s official ones; the Ministry publishes descriptions in Spanish only.